Borough Council continues discussion of bridge replacement project

April 8, 2013

Preliminary sewer line replacement work continues by construction crews from Palo Construction in preparation for the Route 310 and 119 intersection improvement and bridge replacement project this summer. (Photo by Larry McGuire of The Spirit)

PUNXSUTAWNEY — Sewer relocation work will proceed ahead of the Elk Run Route 119 bridge replacement project, which is scheduled to begin this summer after school has let out.

Punxsutawney Borough Council received an update on the Route 119 and 310 intersection road construction project during Monday’s council meeting.

“The sewer line has been revised and reviewed with the borough and sent on to PennDOT for review,” said Ben White, Punxsutawney Borough manager.
White said major work on the bridge and detour will not start until June.

“Palo Construction, the contractor for the project, is planning on doing part of the sewer line relocation this month or in May, ahead of the beginning of the bridge construction, using temporary bypasses,” White said, adding that this would involve a one-lane traffic restriction for short periods of time.

For more from Monday's meeting, see Tuesday's print edition of The Spirit.

BIG RUN — Pennsylvania American Water Company (PAWC) has announced the start of construction to install a concrete wall...
VIDEO OF THE DAY: The Best Tips and Tricks for Christmas Leftovers When the holiday celebration is over you don't have...
Gavin Jache (pictured) will experience the thrill of a life time when he marches and plays in the Salvation Army Band...
Thursday Night Football 12/11/14 Arizona (11-3) 12 @ St. Louis (6-8) 6
Friday night, the Route 36 Rivalry was alive and well, with two different Punxsy-Brookville...

 

Premium Drupal Themes by Adaptivethemes